Critical Path and Gantt Chart help

8 Posts
2 Users
0 Reactions
2,900 Views
(@cdhamilton)
Posts: 8
Active Member
Topic starter
 
[#9577]

Hello ProjeQtOr Community,
I’m setting up a project in ProjeQtOr and would like to confirm if the critical path is being calculated correctly based on my current setup.

Here’s what I’ve done:

  • Work-Packages: Entered all work-packages with appropriate dependencies (e.g., Finish-to-Start, Start-to-Start).
  • Milestones:
    • ​​​​​​​Project Start: Set as the predecessor for the very first work-package.
    • Project Finish: Set as the successor for several terminal work-packages that have no tasks following them. I’ve attached a screenshot of the Gantt chart with the “Show Critical Path” option enabled. 

​​​​​​​
Questions: 
[list=1]

  • Does the critical path appear to be calculated correctly with this configuration?
  • Is there anything I might have set up incorrectly that could affect the critical path calculation?

  •  
    Posted : 23 Sep 2024 12H51
    (@marylene)
    Posts: 592
    Contributor Admin
     

    Hello
    Did you check the box to recalculate your project taking into account the critical path?
    Do you get the same result by doing so?

     


     
    Posted : 25 Sep 2024 12H15
    (@cdhamilton)
    Posts: 8
    Active Member
    Topic starter
     

    Hi,

    I do not have that option. My interface looks different. Please see attached screenshots.


     
    Posted : 25 Sep 2024 12H26
    (@marylene)
    Posts: 592
    Contributor Admin
     

    ouch 
    What version are you working on?


     
    Posted : 25 Sep 2024 12H54
    (@cdhamilton)
    Posts: 8
    Active Member
    Topic starter
     

    Version V10.3.6

    Do you think my critical path looks correctly calculated?


     
    Posted : 28 Sep 2024 11H09
    (@marylene)
    Posts: 592
    Contributor Admin
     

    It's hard to know without having access to your data since it's a critical chain. Whatever happens, it's better that you do a quick update to the latest stable version.

    First, because we only take into account the latest version to help you on the forum and second, since version 10.3 there have been a lot of bug fixes and new features like on the critical path precisely!


     
    Posted : 30 Sep 2024 11H08
    (@cdhamilton)
    Posts: 8
    Active Member
    Topic starter
     

    My university has set up ProjeQtOr and hosts it, allowing us to access it via a provided link. I have previously explored installing it myself and believe I can make my computer the local host. Apologies if my terminology is not accurate. To get the latest version, I will need to install it myself since I cannot dictate my university’s decisions. When I do this, I would be happy to export my project file (if possible) and share it with you so you can review the data and identify any obvious mistakes?


     
    Posted : 30 Sep 2024 12H55
    (@marylene)
    Posts: 592
    Contributor Admin
     

    Great idea! With a Wamp-like server you will be free to follow us at the pace of our new versions and discover our latest features! and you will already be able to see if your critical path still displays the same result!


     
    Posted : 30 Sep 2024 15H47