Hi..
I'm new user in this perfect management software
How the planning draw the days of project ? if it dependence on the date of "validated" or the days of resources work?

as seem in attachments


 
Posté : 16 Juil AM 00:077
(@babynus)
Posts: 14952
Membre Admin
 

Default planning mode (asap) is a capacity planning : you must assign some work on resources to have capacity planning calculated.


 