Planning error or ?
 
Notifications
Clear all

Planning error or ?

2 Posts
2 Users
0 Reactions
1,441 Views
(@dany_313)
Posts: 12
Active Member
Topic starter
 
[#6820]

Hi..
I'm new user in this perfect management software
How the planning draw the days of project ? if it dependence on the date of "validated" or the days of resources work?

as seem in attachments


 
Posted : 16 Jul 2020 0H53
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Default planning mode (asap) is a capacity planning : you must assign some work on resources to have capacity planning calculated.


 
Posted : 16 Jul 2020 13H22