[SOLVED] Closing Project with closed activites :

4 Posts
2 Users
0 Reactions
5,109 Views
 DPo
(@dpo)
Posts: 11
Active Member
Topic starter
 
[#2036]

Hi,
I try to close a project, but after closing all activities, tickets, milestone in the project, I just have a meeting left (any way to close a meeting ?)
, I still have a message disabling the closure of my project :

Invalid controls.
Unable to close an element with left work

Any way to know exactly where it blocks (activities, mailestone, ticket), the message is not explicit enough for me.

Thanks.


 
Posted : 08 Oct 2014 16H12
VAUCHEY
(@protion)
Posts: 138
Active Member
 

Hello

The problem probably comes from the fact that you stay a rest in one spot, the solution and put the rest to 0 in assignments
------------------------------------------------------------------------------------------
Bonjour

Le problème vient sans doute du fait qu'il vous restes un reste dans une tache, la solution et de mettre le reste à 0 dans les assignations


http://www.vkv.iea45.fr/

 
Posted : 08 Oct 2014 16H18
 DPo
(@dpo)
Posts: 11
Active Member
Topic starter
 

That's it, I found that the time left on the meeting was not pointed out, so after bring it to 0, it closed ok !

Thanks.


 
Posted : 08 Oct 2014 16H20
VAUCHEY
(@protion)
Posts: 138
Active Member
 

Good 😛


http://www.vkv.iea45.fr/

 
Posted : 08 Oct 2014 17H49