Hi,
I try to close a project, but after closing all activities, tickets, milestone in the project, I just have a meeting left (any way to close a meeting ?)
, I still have a message disabling the closure of my project :
Invalid controls.
Unable to close an element with left work
Any way to know exactly where it blocks (activities, mailestone, ticket), the message is not explicit enough for me.
Thanks.
Hello
The problem probably comes from the fact that you stay a rest in one spot, the solution and put the rest to 0 in assignments
------------------------------------------------------------------------------------------
Bonjour
Le problème vient sans doute du fait qu'il vous restes un reste dans une tache, la solution et de mettre le reste à 0 dans les assignations
http://www.vkv.iea45.fr/
That's it, I found that the time left on the meeting was not pointed out, so after bring it to 0, it closed ok !
Thanks.