Hello,

Question from one of my users : is it possible to log work both on a Ticket and also separately on the linked Planning Activity ?

Scenario:
- Create a ticket T , linked to planning activity A
- User U is assigned to activity A 
- User logs work on ticket T for 1 day => work is consolidated on activity A
- User also wants to log work directly on activity A 
=> is this allowed ? 

I always try to separate work logged using tickets and work logged directly on an Activity, because it's much simpler to check data that way.
So I don't know really if it is possible to combine both logging work via Ticket and directly on Activity ?

Thanks


 
Posted : 03 Jun 2022 14H10
(@babynus)
Posts: 14952
Member Admin
 

No,
When Planning Activity has tickets, work entry is expected only on tickets.
But this work is consolidated on Planning Activity.


 
Posted : 08 Jun 2022 15H51