hello
i think the reporting will better for report
The choice of the start and end dates ( exemple start 2014/6 end 2016/8) or limit max 60months
Monthly planning project/resource
you can add all monthly ( option tick next month)
same for this reports
Detailed work per resource - yearly
For any kind of report I think 🙂
Sorry, I don't understand the requst, could you explain it a bit more, for instance with some print screen ?
hello
Take example on long projects !!! Or that the manager wants to have a reporting on the fiscal year that is not civil for all companies
Or in my case all the tasks done by my family and child from their beginnings to schools
See capture below
Offer a free choice on the start and end date 🙂 for all report not force monthly yearl civil
Note:
If you give me the SQL query to make reports, we can manually change to have a table view while waiting for the evolution?
Thanking you in advance
OK, I understand better now.
Request recorded as Ticket #2380