We have a problem exporting and reopening a project (gantt) from Projeqtor.
The duration of the tasks don't match.
Example on the first 2 tasks on battached pictures :
- 'Input data definition ' task : 3 days on Projeqtor goes to 0.6day on MS project.
- "Product design" task : 20 days on projeqtor goes 4 days on MS project.
Have you ever seen this issues? Do you have a solution to are able to open the datas on MS project with the correct task durations.
Thanks for your help.
I guess it is because MS-Project does not manage Pools.
Moreover, you are using a "unique resource" planning for the pools.
MS-Project does not understand and uses full pool capacity...
This is a limit of export/import with tools than don't plan the same way.