[v6.1.0 acceptance review] - KPI duration for project

3 Posts
2 Utilisateurs
0 Reactions
2,532 Vu
(@verges)
Posts: 85
Active Member
Début du sujet
 
[#4177]

Hi,

I don't understand calculation for 1 project.

Duration KPI for project is calculated with this formula KPI duration = (End validated date - start validated dates ) - (end planned date- start validated date).

I don't understand why you use "start planned date" in the calculation?

The reference date is the "start validated date" .....

Regards


 
Posté : 6 Mar PM 18:033
(@babynus)
Posts: 14952
Membre Admin
 

Because KPI Duration is (Validated duration) - (Planned Duration)
Look above :
I

Planned duration is equal to validated duration.

If you replace "start planned date" with "validated start date" you don't get a Duration KPI, but a "delivery delay" KPI.


 
Posté : 6 Mar PM 22:033
(@verges)
Posts: 85
Active Member
Début du sujet
 

You are right,

Thanks you for precision. In our organization we are focus on "delivery delay KPI" . It is the reason why...

Thanks,

Regards,


 
Posté : 7 Mar PM 15:033