Hi,
I don't understand calculation for 1 project.
Duration KPI for project is calculated with this formula KPI duration = (End validated date - start validated dates ) - (end planned date- start validated date).
I don't understand why you use "start planned date" in the calculation?
The reference date is the "start validated date" .....
Regards
You are right,
Thanks you for precision. In our organization we are focus on "delivery delay KPI" . It is the reason why...
Thanks,
Regards,