[v6.1.0 acceptance review] - KPI duration for project

3 Posts
2 Users
0 Reactions
2,549 Views
(@verges)
Posts: 85
Active Member
Topic starter
 
[#4177]

Hi,

I don't understand calculation for 1 project.

Duration KPI for project is calculated with this formula KPI duration = (End validated date - start validated dates ) - (end planned date- start validated date).

I don't understand why you use "start planned date" in the calculation?

The reference date is the "start validated date" .....

Regards


 
Posted : 06 Mar 2017 18H02
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Because KPI Duration is (Validated duration) - (Planned Duration)
Look above :
I

Planned duration is equal to validated duration.

If you replace "start planned date" with "validated start date" you don't get a Duration KPI, but a "delivery delay" KPI.


 
Posted : 06 Mar 2017 22H16
(@verges)
Posts: 85
Active Member
Topic starter
 

You are right,

Thanks you for precision. In our organization we are focus on "delivery delay KPI" . It is the reason why...

Thanks,

Regards,


 
Posted : 07 Mar 2017 15H35