Calendar options for an international project team

2 Posts
2 Users
0 Reactions
1,284 Views
(@giovannino)
Posts: 14
Active Member
Topic starter
 
[#7690]

Hello,
I was wondering how to set a mixed calendar where some resources work from Monday to Friday and other resources work from Sunday to Thursday .
Is it possible to have multiple calendars for the same project ?
Thanks 
Giovanni


 
Posted : 12 Aug 2021 21H10
(@alain-fourastie)
Posts: 366
Member Moderator
 

hi
A resource is allocated by only a single calendar. whatever it is. You must create as many calendars as types of resources how they show up during the week


 
Posted : 13 Aug 2021 11H16