Hello,
I was wondering how to set a mixed calendar where some resources work from Monday to Friday and other resources work from Sunday to Thursday .
Is it possible to have multiple calendars for the same project ?
Thanks
Giovanni
Posté : 12 Août PM 21:088
hi
A resource is allocated by only a single calendar. whatever it is. You must create as many calendars as types of resources how they show up during the week
Posté : 13 Août AM 11:088