Calendar options for an international project team

2 Posts
2 Utilisateurs
0 Reactions
1,281 Vu
(@giovannino)
Posts: 14
Active Member
Début du sujet
 
[#7690]

Hello,
I was wondering how to set a mixed calendar where some resources work from Monday to Friday and other resources work from Sunday to Thursday .
Is it possible to have multiple calendars for the same project ?
Thanks 
Giovanni


 
Posté : 12 Août PM 21:088
(@alain-fourastie)
Posts: 366
Membre Moderator
 

hi
A resource is allocated by only a single calendar. whatever it is. You must create as many calendars as types of resources how they show up during the week


 