I finished ! when you are piloting by effort (ie filling in the timesheet to advance the progress of an activity) how do you do if the activity is finished before the time initially planned?
***
j'ai fini !
quand on est au pilotage par l'effort (c'est à dire que l'on rempli la feuille de temps pour faire avancer l'avancement d'une activité) comment fait on si l'activité est fini avant le temps initialement prévu ?
hi,
then recalculated projects will take into account this fact.( with shared resources )
you can close, if you want, this project. it won't be displayed anymore.
thank you but I don't understand well,
I will enter the times in the timesheet either it will be more or it will be less how will the software know if I have finished the activity in question? is the statute saying so? for example when it will be "done"
***
merci mais je ne comprends pas bien,
je vais rentrer les temps dans la feuille de temps soit ça sera plus ou ça sera moins comment le logiciel va savoir si j'ai fini l'activité en question ? c'est le statut qui le dit ? par exemple quand il sera "done"
Status do not impact the planification and calculation. You can track each stage of your projet changing manually status depending on a single workflow dedicated to a type.
IN global parameters you can set up some mechanisms related to the beginning or the ending workload on each activity impacting the display of general status ( in progess and done)
To know if you re in advance or late you ve just to compare your situation with WHAT YOU VE EXPECTED ( on column for validated dates ) . it is your own appreciation , your own business with your customer that you had validated on the past. In the meantime Real live took place ( work made as planned ? , workload changes ? others modificationabout the perimeter ? ) so forecasting and steering the deviations seems to be easy comparing both of them ( the end date expected - the real end date given by the application )
To sum up : A project could be done ( generally when remainding work is zero) either late either just in time or in advance, Compare end date ( it is done) or planified end (during your project) date with validated end, and you will know if you are or in a good or wrong way.
Just set left work to zero.
thk '
a quick question in the timesheet for a day;
1 = FTE
if that's right for an 8h day, 1h = 0.125; and if we do more well we exceed we can therefore have 1.25 if a day of 10h?
***
une petite question dans la timesheet sur une journée;
1 = ETP
si c'est bien ça pour une journée de 8h, 1h = 0.125 ; et si on fait plus ben on dépasse on peut donc avoir 1.25 si journée de 10h ?
NO 8H or 10 H is always 1 the loadwork could be planned and worked PER DAY.
PLEASE SEE global parameter work time unit for work.
yes you have to decide if you imput by hours or by part of days or by part of hours by day
1h = 0.125d for a 8h day, yes.
thank you !
and if not what does it do when we click on "validate" after "submit" in the 1st line?
and also what is "enter real as planned"?
I read the manual and understood that it was not very useful for me who am on my own
Moreover, for example, if we don't do the day's work, is it recalculated on the schedule?
thank you
****
merci !
et sinon ça fait quoi quand on clique sur "valider" après "soumettre" dans la 1ere ligne ?
et aussi c'est quoi "entrer réel comme planifié" ?
j'ai lu le manuel et j'ai compris que ce n'était pas très utile pour moi qui suis tout seul
par ailleurs, est ce que par exemple si on ne fait pas le travail du jour est ce que c'est recalculé sur le planning ?
merci
Yes and Yes