Error when calculating planning in view Planning (No data to display)

14 Posts
2 Users
0 Reactions
8,190 Views
(@msassi)
Posts: 8
Active Member
Topic starter
 
[#6639]

Hello,
Recently, I installed projeqtor V8.2.4
- I did my best to configurate projeqtor in interafce "global paramters". (Please see screenshot attached below)
- I created a custom workflow, project, some ressources
- I added some activities where ressources are assigned

Then I openned interface "Planning". Unlucky, I have following problems with planning :
- Not all planning are displayed. Planning is displayed only till current day. Only activities that were already filled by ressources into timesheet are displayed. (Please see screenshot attached below)
- 2 off days (Saturday and Synday) don't have grey colour. They are not shaded (Please see screenshot attached below)
- When right click into activity planned in current day, I have error "No data to display. Planning calculation required" (Please see screenshot attached below)

I need to get a complete planning.
Any help please.

Thank you in advance.


 
Posted : 15 Apr 2020 3H26
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Message in pop-op (at right click on bar) is clear : you need to calculate planning (use big gear button on planning screen)


 
Posted : 17 Apr 2020 11H18
(@msassi)
Posts: 8
Active Member
Topic starter
 

Hello,
If you mean button that I mentionned in attached screenshot, I answer that it doesn't resolve problem. (Please take look below to screenshot)
I used it since first time, and however planning is calculated I have always same problem.

Thank you in advance


 
Posted : 18 Apr 2020 3H34
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

When you click on this button, you get the list of projects that will be calculated.
Be sure to select your project and click OK.
Please post new screenshot afterward.


 
Posted : 18 Apr 2020 21H25
(@msassi)
Posts: 8
Active Member
Topic starter
 

I did it but I have same error 🙁 (Please see below screenshot)
I selected "All project", then I selected only my project and finally I selected all project I have but no way


 
Posted : 18 Apr 2020 22H04
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

OK,
So your project or task is not planned.
Several possible reasons :
- you don't have right to calculate planning for this project
- project is administrative (lokk at project type)
- project has "fix planning" (look at value for checkbox)
- task has "fix planning" (look at value for checkbox)


 
Posted : 19 Apr 2020 15H51
(@msassi)
Posts: 8
Active Member
Topic starter
 

Hello,
It seems that reason that you sent to me are not tthe cause of my problem.
I ckecked it one by one in my project but problem is not resolved.

I taked 14 screenshots from differents UI in my ProjeQtor that I thought they could contain the cause of my problem.
Please find in attached a .zip

We choose projeqtor between many are solution because we like too much how planning is calculated.
Hope that we could together find solution for this.

Thank you in advance


 
Posted : 24 Apr 2020 4H17
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

Your resource #3 has capacity (FTE) = 0
It means he can work 0 days per day.
This explains why the planning gives no result.
Chenge Capacity to 1 (standard value) to have planning work.


 
Posted : 24 Apr 2020 11H04
(@msassi)
Posts: 8
Active Member
Topic starter
 

Hello,
After following your last mail, we have only one problem resolved. (in relation with timesheet)
Now, colors in timesheet are well displayed ('Green' for all working days with 8 hours and 'Red' for off days).

But, planning calculation still not working !

Any help please. Could you take a look again to all screenshot that I sent in others messages.

Thank you in advance.


 
Posted : 30 Apr 2020 20H09
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

When capacity is fixed, recalculate planning.
If planning is not calculated, check allocation rate to project : it must not be 0 on projct and on parent projects.


 
Posted : 01 May 2020 16H43
(@msassi)
Posts: 8
Active Member
Topic starter
 

If we well understand "Rate", it's column "Rate" into project/Allocation to project.
Please take a look to screenshots we attached to this ticket and check with us if rate is well done.

Else , we always have doubt that probems are caused by fields into "Dates and durations" into every activity. There are always empty.
But when ressource fills into timesheet and "real time" of activity becomes > 0, planning is well calculated (Look please to screenshots called "Real_time_1.png" & "Real_time_2.png")


 
Posted : 01 May 2020 18H30
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,
On your screenshot I can see that left work is zero.
So there is nothing more to plan...


 
Posted : 02 May 2020 16H17
(@msassi)
Posts: 8
Active Member
Topic starter
 

Sorry, please take a look again to screenshots and especially to picture called "Real_time_2.png".
Picture "Real_time_1.png.png" was sent to show you that planning is calculated only for activity that has "Real time > 0 ".

Is it possible to have live chat or maybe via Skype, What's app ... ?

Our project and team are growing and we need to solve this problem in order to decide if we will continue with projeqtor or not.
We chose projeqtor because we liked too much planning calculation and until now it doesn't work for us.

Thank you in advance for your understanding.


 
Posted : 06 May 2020 20H57
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

Sorry, please take a look again to screenshots and especially to picture called "Real_time_2.png".
Picture "Real_time_1.png.png" was sent to show you that planning is calculated only for activity that has "Real time > 0 ".

On real_time_1, you don't have planning, but display of real work.
So I guess your project is not correctly calculated for some reason.

Is it possible to have live chat or maybe via Skype, What's app ... ?

Not on free support on this forum.
This can be provided only to customers subscribing to our support service.

I'm sure there is something in your configuration that forbids planning calculation. This can be :
- fix planning flag on the project.
- allocation rate to zero : this must be controlled on the project and on parent projects, up to top level (the restriction on allocation rate is controlled on the whole hierarchy).
- assignment rate to zero
- capacity of resource to zero
- calendar with no oppen day


 
Posted : 10 May 2020 15H04