Hello,
can you define the calculation rules for this report, when a team are selected ?
Thanks.
Bruno.
Hi,
For each member of the team, we compare "Validated Work" to "Reassessed work" (real + left)
Value = 1 => resource did exactly what was planned
Value resource worked faster than expected
Value > 1 => resource worked more time than expected
Perfect thanks