[SOLVED] definition of Report steering charts/performance indicator

3 Posts
2 Users
0 Reactions
1,836 Views
(@pipobru)
Posts: 180
Active Member
Topic starter
 
[#6635]

Hello,
can you define the calculation rules for this report, when a team are selected ?
Thanks.
Bruno.


 
Posted : 14 Apr 2020 13H58
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

For each member of the team, we compare "Validated Work" to "Reassessed work" (real + left)
Value = 1 => resource did exactly what was planned
Value resource worked faster than expected
Value > 1 => resource worked more time than expected


 
Posted : 14 Apr 2020 14H51
(@pipobru)
Posts: 180
Active Member
Topic starter
 

Perfect thanks


 
Posted : 14 Apr 2020 16H21