Problems with activity duration

6 Posts
2 Users
0 Reactions
4,024 Views
(@montagnard)
Posts: 9
Active Member
Topic starter
 
[#2667]

Hi,
I'm trying to set my project planning, but I faced to a problem :
- The duration of an activity is much longer than it must be... I planned 1,5day and the activity is planned with 27days. I don't understand why, could you help me ?
You'll see the details in the attached files

Thanks!


 
Posted : 23 Oct 2015 12H06
(@babynus)
Posts: 14952
Member Admin
 

Did you define affectation start date for one of the two assigned resources ?


 
Posted : 23 Oct 2015 13H12
(@montagnard)
Posts: 9
Active Member
Topic starter
 

No, I don't do that. Where can I check to be sure ?


 
Posted : 23 Oct 2015 18H37
(@babynus)
Posts: 14952
Member Admin
 

In affectation list, that you'll find in 3 points :
- affectation list in the resource screen
- affectation list in the project screen
- affectation screen


 
Posted : 23 Oct 2015 18H42
(@montagnard)
Posts: 9
Active Member
Topic starter
 

After a quick check, i'm sure, there isn't any start date for both resources


 
Posted : 23 Oct 2015 18H46
(@babynus)
Posts: 14952
Member Admin
 

Could you show tasks before the one in issue ?
I guess assigned resources are busy on other tasks.
Please also check (and possibly display) report "planning">>"Monthly planning resource/project/activity".


 
Posted : 23 Oct 2015 20H39