Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hi,
How do can change the order of the project to show in the Global planning project/resource per month report? At the moment the report is ordered by id. However I would like to have it alphabetically.
Thanks!
At the moment the report is ordered by id.
No, it is sorted by WBS.
Just move project to reorder them as expected on Gantt view.
OK, in my case, the result is the same as ordered by ID. I didn't realize that I can reorder it in the planning Gantt view...
Thanks!