Hi,
How do can change the order of the project to show in the Global planning project/resource per month report? At the moment the report is ordered by id. However I would like to have it alphabetically.
Thanks!
Posté : 27 Mar PM 14:033
At the moment the report is ordered by id.
No, it is sorted by WBS.
Just move project to reorder them as expected on Gantt view.
Posté : 27 Mar PM 15:033
Début du sujet
OK, in my case, the result is the same as ordered by ID. I didn't realize that I can reorder it in the planning Gantt view...
Thanks!