[SOLVED] Project ordered alphabetically in Planning report

3 Posts
2 Users
0 Reactions
1,978 Views
 Moqi
(@clarezoe)
Posts: 73
Active Member
Topic starter
 
[#5872]

Hi,

How do can change the order of the project to show in the Global planning project/resource per month report? At the moment the report is ordered by id. However I would like to have it alphabetically.
Thanks!


 
Posted : 27 Mar 2019 14H53
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

At the moment the report is ordered by id.

No, it is sorted by WBS.
Just move project to reorder them as expected on Gantt view.


 
Posted : 27 Mar 2019 15H20
 Moqi
(@clarezoe)
Posts: 73
Active Member
Topic starter
 

OK, in my case, the result is the same as ordered by ID. I didn't realize that I can reorder it in the planning Gantt view...

Thanks!


 
Posted : 27 Mar 2019 15H47