Working time vs activity's responsible/pool of ressources

2 Posts
2 Users
0 Reactions
2,079 Views
(@fmartin)
Posts: 43
Active Member
Topic starter
 
[#6718]

Good morning,

i have noticed that when you assign a pool of ressources to an activity with x days, the working time spreadsheet gets wrong when the responsible of the activity is within the pool of ressources.

It seems that if the responsbile of the activity is within the pool, it does not take it into account and create automatically a new line on the assignation for the responsible.

Therefore, the calculation gets wrong as I want to assign X days to the pool and that's it. I don't want that line to interfere with the assignation.


 
Posted : 20 May 2020 9H58
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

hi,

A solution consist on going to "global parameters" then "activity" then " automation" and choose "no" at the line "auto set responsible if single resource"

Best regards


 
Posted : 20 May 2020 10H56