Forum

Working time vs act...
 
Notifications
Retirer tout

Working time vs activity's responsible/pool of ressources

2 Posts
2 Utilisateurs
0 Reactions
2,042 Vu
(@fmartin)
Posts: 43
Trusted Member
Début du sujet
 
[#6718]

Good morning,

i have noticed that when you assign a pool of ressources to an activity with x days, the working time spreadsheet gets wrong when the responsible of the activity is within the pool of ressources.

It seems that if the responsbile of the activity is within the pool, it does not take it into account and create automatically a new line on the assignation for the responsible.

Therefore, the calculation gets wrong as I want to assign X days to the pool and that's it. I don't want that line to interfere with the assignation.


 
Posté : 20/05/2020 9:58 am
(@alain-fourastie)
Posts: 366
Membre Moderator
 

hi,

A solution consist on going to "global parameters" then "activity" then " automation" and choose "no" at the line "auto set responsible if single resource"

Best regards


 
Posté : 20/05/2020 10:56 am
Share:
Retour en haut