ok, I checked: table milestone: the milestone was not found table: planningelement: milestone found --> deleted and planning is fine now ...
Thank you! Do you need any further informations or details?
Hello Kitcat, you could check this out: Problem with planned end date
I use always the same profile (Projectleader). To clarify the structure and affectations I made some screenshots... Access to data Organizatio...
Thanks very much. I tried both solutions and both work 🙂
Yes, we use already V6.2.5 Do you need any more niformation?
I did it already. So the bar in the gantt chart has 'slipped' to the correct date. But the written planned end date in the activity didn't change. An...
ok I found the issue. I have the following structure: Main project (administrative) |- Subproject (administrative) | - sub-sub-project (int...
We would need more than a Gantt Chart. It should be an overview of the work packages like the attached file . Is there any similar at the current ...
Hi all, I have an additional, very simliar question: I have limited the ressources view to team/organization. This works e.g. in ressource plan...
Thank you very much for the answer. So there is now way to remove one resource to one subproject ?! Because the Master Project leader needs his ...