Thanks Babynux, I can't change it because I choose this planification mode because this ressource is not working at 100% on projects but sometimes,...
Thanks climb4fun I tried on the demo and it works fine but I understand, in my config, all works and real work allocation are working with hours bu...
Thanks.
No, planning is defined form Left wor, an integrates real work also.. Yes, you are right, (I use it to manage the indisponibility as half day, holi...
How the planning could be right if you have no validated/assigned work for the ressource (i.e.because you just enter a real work allocation)? In my...
So, what is the difference between sub project and sub task?
Yes but it is not displayed on the Planning, we can enter a real work but the planning is wrong.
Thanks a lot Babynus. B)
Any suggestion?
You are right but in the real world, sometimes we need plan to a specific date that's why in ProjeQtOr, some plannings cannot reproduce the reality. N...
Hi Babynus, do you think it is a possible evolution?
No problem, I understand 🙂 It was just to have a more clear road map because this behavior is generated some "wrong planning" (i.e. some tasks w...
2 CPU and 6GB RAMWill be quite enought for about 10 simultaneously connected users. 10 simultaneously users : doing something as recalculate planning...
Hi Babynus, Do you have an estimated date or version for this evolution? Thanks.