Topic
8 years ago
Replies: 3
Views: 2970
Reply
Kanban download

Fine , But when i click on forgotten password with the same mail address on my inovice i never receive the new password

8 years ago
Topic
8 years ago
Replies: 3
Views: 2728
Reply
Ticket & Cost

for each tickets I spend time but also Euros. thank you for your reply

8 years ago
Topic
8 years ago
Replies: 3
Views: 2763
Topic
9 years ago
Replies: 1
Views: 2955
Reply
Ticket view & right

Thank you in fact, i have severals team on the same project. each team manager must see only his team. regards

9 years ago
Reply
9 years ago
Topic
Replies: 7
Views: 7505
Topic
Replies: 1
Views: 3267
Reply
ticket responsible

thank you for your reply. i understand, but "external team member" have this profil only on kind of project. They can also resource on other project.

9 years ago
Topic
Replies: 2
Views: 2796
Reply
9 years ago
Topic
Replies: 2
Views: 2543
Reply
[SOLVED] planning /Activties

Hello But in my case it's not possible, i have several team (resources) for the same step "Fabrication" and i have to see the charge for all teams ...

9 years ago
Reply
[SOLVED] planning /Activties

thank for your reply i work for construction constuction company. 4 step : foundation, fabrication, erection , sub-trade. i need see the projec...

9 years ago
Reply
[SOLVED] planning /Activties

ok i see. but... projet have activity. (foundation, production, erection) . how i can see "with planning view" the foundation activity for all proje...

9 years ago
Topic
Replies: 6
Views: 6721
Reply
[SOLVED] planning /Activties

thank you ! it's ok now

9 years ago
Topic
Replies: 2
Views: 3210
Topic
Replies: 0
Views: 3
Reply
[SOLVED] Kanban column

Ok i 'll check why it's not good for me. another ask. in activity is set the estimate charge but in kanban i have 0.