I am trying to evaluate this software to try and determine if it should be short listed for use at the company I work for. I managed to create a new project BH test 1 in the demo area. Added activities, managed to plan in the gantt chart. However does seem to be any way to get activites and project in the time sheet to enable allocated roles to enter hours spent.

Please see attached document for more details project activities not appear in timesheet.

Thanks


 
Posté : 31 Oct PM 17:1010
(@babynus)
Posts: 14952
Membre Admin
 

You project is checked "under construction".
So resource cannot start entering work.
Uncheck "under construction", lines will appear on timesheets.


 