Hi,
when i have many project affected to a ressource
I have a problem in the menu REAL WORK ALLOCATION, the ressource can't save his imputaions because the big number of the activity assgnied so when i want to chek the option show clos elements. the problem when i put some activity as clos the problem persist and the activity that are supposed to be closed are n't.
would u suggest a solution for this
When you have these kind of error, you'll find more information in the log file.
Please report it here.
the error is "maybe the max_input_var are Insuffisant in th php.ini"
It is a well know issue, due to max_input_vars, introduced by PHP 5.3.
Solution is already described in several posts
http://projectorria.toolware.fr/index.php/forum/5-ask-questions/3804-error-in-imputation
http://projectorria.toolware.fr/index.php/forum/5-ask-questions/2650-error-modify-imputations
http://projectorria.toolware.fr/index.php/forum/2-submit-issues/2035-unable-to-save-any-hours-worked