Hello, in my project the following situation occurs:
John works on Mondays and Thursdays from 6pm to 9pm.
Joe works on Tuesdays and Fridays from 7pm until 11pm.
Mary works on Saturdays and Sundays from 12am until 8apm.
How I can assign this calendar to each of them in order to assign them to control my activities and projects?
thank you very much
In current version, you can't.
All you can define is :
- John has capacity of 3 hours a day (capacity = 0,375 for a 8 hour day)
- Joe has capacity of 4 hours a day (capacity = 0,5 for a 8 hour day)
- Mary has capacity of 8 hours a day (capacity = 1 for a 8 hour day)
Then affect each resource at a rate of 40%, to insure they work only 2 days a week.
Weekly work planning will be correct, but you won't be able fix days really planned for each.
Calendar per resource is an already identified evolution (Ticket #714), not really planned yet.
Hello Babynus and danyengel2,
The ability to set the days and hours of work can make a real flexibility for the allocation and control of activities and projects. Otherwise, when teams are important, the manager must be a good mathematician ...
This function is welcome 🙂