same Project type ?
Yes
same allocations ?
Yes
Do you think it can come from the fact that we created the project "TEST 2" after putting the parameters of automatic calculation ?
Can you try and restart the CRON system ?
Are the two projects correctly calculated ?
If it works, it may be an access rights issue ...
I have done what you suggested and it works now.
I have checked on 4 projects and they have been calculated automatically.
So we have to restart the CRON system after changing the parameters ?
EDIT : Actually, I have checked on another project that has been created at 5:37PM but it has not been calculated (knowing that the automatic calculation is at 7PM). It has the same type and the same team of others.
So we have to restart the CRON system after changing the parameters ?
No, this is already done.
But I guess there is an issue on access rights : cron does not retrive correct rights for projects created after it was launched.
I created ticket #3786 to fix this issue.
Hello,
If I am not wrong, I have seen that the problem has been fixed.
If we upgrade to 7.3.5, we won't have this problem anymore ? (we are in 7.2.7)
Regards,
Yes, ticket #3786 has been fixed on V7.3.4