Please explain what you wnat to do, what you get and what what is your problem.
It's not clear with just a screenshot.
I do not understand why the planned deadlines are different from the validated deadlines.
1. I enter activities in chronological order
2. I link the activities for automatic scheduling
when I run the automatic calculation the validated deadlines do not correspond to the planned deadlines!
Why?
See attachement please.
thanks
Becasue unless you define activities with planning mide "regular between dates", validated dates are not taken into account to calculate planning.