Hello,
I've got a project and an activity. I wnated to call for an externe in order to help me in that project. For instance in his function "F1' i set default cost to 150€ (i assume it's the cost per day ). But when this externe enter real work ( 9 days at the moment)on the activity the cost of the project doesn't change while it should have been 150*9. Am i doing something wrong?
here's the allocation of the extern and his function
Never mind I just had to relog and changes were applied
This point had already been identified and is subjet of an improvement on V7.1.0