[#5186]

Hello,

I would like to know if it's possible than gantt after "real work allocation" for exemple 0.5 day on 2 days left work , the gantt keeps the bar visible for 2 days.
Because currently this leads to a bad interpretation of the gantt by some people (see sample in file attached ).

Thank you.


 
Posté : 24 Mai AM 11:055
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

I cannot reproduce the issue
From same case

after entering real

So all seems correct.

Could you please detail use case, and explain why assigned work has changed (from 2 to 2.5) ...


 
Posté : 24 Mai PM 15:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

Hi,

Sample with doc see attached

Thanks


 
Posté : 24 Mai PM 16:055
(@alain-fourastie)
Posts: 366
Membre Moderator
 

HI
Have you done something else, like for instance, modify the FTE of this ressource before launching the calculation ?


 
Posté : 24 Mai PM 19:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

Hi,

I create only an activity on 2 days by example
After , i allocated a ressource for 2 days
After in the real work allocation , i have imputed 0.5 day and save (with the icon diskette)

After a check, i see than : start date and end date (in PLANNED) are complete on the date imputation, maybe it's anormal ....


 
Posté : 24 Mai PM 19:055
(@alain-fourastie)
Posts: 366
Membre Moderator
 

hi
Could you check, please, the value of FTE of this resource when you allocate it to this project. Is it 2 on this box ? (and not a value beetween 0,1 and 1 as expected)


 
Posté : 25 Mai AM 11:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

Hi,

Where is FTE value ?


 
Posté : 25 Mai AM 11:055
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Select the resource, on détail area please fill capacity box ( FTE) . the value 1 means that the resource works all day long, O,5 indicates half a day.(opened hours)


 
Posté : 25 Mai AM 11:055
(@babynus)
Posts: 14952
Membre Admin
 

Could you also precise which version of ProjeQtOr you are using ?


 
Posté : 25 Mai AM 11:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

See detail in file attached for this example
2days
0,5 real work alloction

Version Projeqtor V7.0.8


 
Posté : 25 Mai AM 11:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

And for information the definition in parameter of the work time


 
Posté : 25 Mai AM 11:055
(@alain-fourastie)
Posts: 366
Membre Moderator
 

please select the icon resource. Then select on the list your resource. click on it. you get the detail as shown below.


 
Posté : 25 Mai PM 12:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

FTE = 1 in this detail for this ressource


 
Posté : 25 Mai PM 12:055
(@alain-fourastie)
Posts: 366
Membre Moderator
 

IT does not help me ;-).... still trying to undestand.


 
Posté : 25 Mai PM 12:055
(@jcroize)
Posts: 35
Active Member
Début du sujet
 

Yes, it's Strange. This problem is arrived with the lasts versions before all was correct :(.
I check the global parameters but i think all are OK.

My PHP is V5.4 but i think than it's not the problem.


 
Posté : 25 Mai PM 13:055