Hi,

I would like to add to my planning some events that need some ressources (seminar for example) and in consequence, those ressources won't be available to work on projects.
What is the best way to manage that?


 
Posted : 09 Jul 2019 19H33
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Use meetings.
Or you can also use Activity with planning mode "regular between dates" and assign work equal to duration or activity.


 
Posted : 13 Jul 2019 20H41