Hello,
with the las t version (8.1.0) for pool of ressources, availability are null without affection (no charge) and negative if a charge are planned. See scren in attachement. may be the bug #4035 is not fuly efficient ?


 
Posté : 9 Juil PM 14:077
(@babynus)
Posts: 14952
Membre Admin
 

It is normal.
It is to have correct SUM for each column (month).

Availability of Pool is already counted as availability of resources in the pool.
So all planned work on pool is something that will decrease availability of resources (but we don't klnow wich, it can be any of the resources of the pool).


 