Please could you remake this typical case over our data base https:demo.projeqtor.org.
Thanks.
yes, but with which account for access at : ressources/real work allocation/ activites /
Thanks.
Hi,
Project :
toto_test-jcro
After test: same problem
Erratum,
No, it's ok on your site.... 🙁
So just try and migrate to V7.0.9 (same version as Démo)
V7.0.9 is installed, same problem 🙁
Could you send to me yours all global parameters ?
And how have you some colors on the gantt ?
Thanks.
Did you refresh browser cache after migration ?
Hi,
I have the solution, it's only " activate/desactivated auto calculation " on gantt is not validated and now it's OK, but this choice modify my dates on PLANNED and impossible to change these values.
Yes, planned dates are result of planning calculation 😉
the calculation with What ???
Have you the rules of calculation ?
Thanks
the calculation with What ???
Calculation with assigned work...
Have you the rules of calculation ?
RTFM