How to organize a Project to obtain sub-totals of validated work

2 Posts
2 Users
0 Reactions
3,261 Views
(@badgamme)
Posts: 32
Active Member
Topic starter
 
[#1924]

Hello,
In a project I created activities with type "Phase" and others (sub-activities) with type "Task" to order my stuff.
So I got a phase nammed "Analysis" with some tasks and a phase "Development" with others.

My questions :
1- is it the right way ? What's the impact of activity type on the behavior of the application ?
2- why didn't I get, in my phase, the amount of "validated work" of the sub-activities ?

Thank you


 
Posted : 29 Jul 2014 14H17
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

is it the right way ?

Yes, It is a good way

What's the impact of activity type on the behavior of the application ?

Some fileds may be defined as mandatory depending on type. Also, workflow can be different.
Have a llok at Type fields.

why didn't I get, in my phase, the amount of "validated work" of the sub-activities ?

Because it is designer this wa : in most cases, you don't know the validated work for sub-activities but for main ones, or just for phases.
So your entry should not be erase by null vlues of sub-activities.
An improvement will come in V4.4 to define how you'd like to sum-up validated work .


 
Posted : 29 Jul 2014 14H34