Impact of priority of phase task (parent) on child task on planification

2 Posts
2 Utilisateurs
0 Reactions
1,983 Vu
 HEU
(@quantamedical)
Posts: 58
Active Member
Début du sujet
 
[#5836]

We read that planification were based on multiple aspects :

  • Dependencies
  • Prioritized planning elements
  • Project priority
  • Task priority
  • WBS

Does the priority of a parent element have an impact on the planning calculation, if yes to what extent?

Thanks for your replies


 
Posté : 14 Mar AM 11:033
(@babynus)
Posts: 14952
Membre Admin
 

No, priority of parent is not inherited.
It has no effect.


 
Posté : 15 Mar AM 11:033