Is the indicator of compliance with the requested end date compared with the actual date or the planned end date?
the comparison with the planned end date makes it possible to identify further upstream if the planning is coherent, whereas the comparison with today's date will too often be too late depending on the duration of the tasks involved.
Thanks for your replies
It is compared to actual date.