Is there a possibility to change automatically the status at start/end date?

3 Posts
2 Users
0 Reactions
1,154 Views
(@coasterman)
Posts: 127
Active Member
Topic starter
 
[#8503]

Hello

Is there a way to configure a workflow/project or something else so that the system changes the state automatically from a defined state at the start date to "in progres" and at the end date to "done" including the booking of the time of the assigned resource?

Regards


 
Posted : 19 Sep 2022 15H35
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

One mecanism exists that can be configured on global parameters
 - on first input of real work, the activity move to first "in progress" status
 - on last input of real work (when left = 0), the activity moves to first "done" status.
You also have an option on global parameters
 - when first sub-activity (of an activity or project) moves to "in progress", the activity move to "in progress"
 - when last sub-activity (of an activity or project) moves to "done", the activity move to "done"


 
Posted : 20 Sep 2022 11H37
(@coasterman)
Posts: 127
Active Member
Topic starter
 

Thank you for the answer.

So, there is no way to fully automate a status change.


 