Planning a specific task

2 Posts
2 Users
0 Reactions
1,007 Views
(@c-munoz)
Posts: 7
Active Member
Topic starter
 
[#8973]

Hello,

I have a problem when planning a task. I have a task that lasts 1 year. Every month I want to plan 2 days for this task. However if in reel time (in the timesheet) I end up not spending 2 days, but 1 for example I don't want the remaining day to "transfer" to the next month when I recalculate my planning. I cannot put "0" in the "left work" because I still have work to do during the coming months. In other words, whatever the time spent in the past, I don't want the future months to be impacted and I want to keep only 2 days per month of work. Do you have a solution ? What planning mode should I use?

(I'm using version 10.4.2)

Thank you,
Best regards,

Cléa MUNOZ


 
Posted : 20 Jul 2023 16H45
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Best is "recuring" planning mode.
But this is planned on a weekly basis.
So you can plan 0.5 every monday, for instance, it will be about 2 days per month.
And it will behave exactly as you expect


 
Posted : 21 Jul 2023 17H07