How should I setup the schedule when several sequential activities (work effort i.e. 1 to 2 hrs each) need to be planned on the same day ? Currently, they are linked (successor) and the planning calculator plans each activity on a different day. The allocated resource has the capacity to work on more activities/day. Thank you.


 
Posted : 20 Jul 2023 19H21
(@babynus)
Posts: 14952
Member Admin
 

Set the "strict dependencies" parameter to 'No' in Global Parameters.


 