Hello ProjeQtor Team,
1) Beginning of september I've created a project with its tasks, resources & assignments. It was perfect. I did create a project kick off baseline.
2) Beginning of october, I would like to update the project progress. Nothing occured in the meantime.
3) When I open the project, it is recalculated to the current date. (normal).
4) But when I recalculate the project at the kickoff date (with "=11.0ptPlan with overuse (infinite overbooking capacity)" => no interaction with over project) it has nothing to see with the kick off situation. Every thing has been replanned in a different way. What did occur ?

Thanks in advance for clarification.
#L.


 