Hi,
Thanks for this incredible software,
I'm using the planning calculation and I want to know
In which case the end-of-start predecessor is not taken into account in the planning calculation?
When i create the dependency to end-start the two tasks are planned one after the other.
For the 2 tasks : each one assigned to a different resource
Run planning again : tasks are planned in parallel.
Thanks,
Hi,
Dependencies are not taken into account :
- when successor is already started (real start date is set)
- when tasks has somle "fix" mode : regular between dates or manual planning
But it seems there is an issue is some case on V8.5.5
We are investigating.