Forum

Predecessor End-Sta...
 
Notifications
Retirer tout

Predecessor End-Start is not taken into account in the planning calculation

2 Posts
2 Utilisateurs
0 Reactions
1,572 Vu
(@ridjy)
Posts: 1
New Member
Début du sujet
 
[#6922]

Hi,
Thanks for this incredible software,

I'm using the planning calculation and I want to know
In which case the end-of-start predecessor is not taken into account in the planning calculation?

When i create the dependency to end-start the two tasks are planned one after the other.
For the 2 tasks : each one assigned to a different resource
Run planning again : tasks are planned in parallel.

Thanks,


 
Posté : 15 Sep PM 16:099
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

Dependencies are not taken into account :
- when successor is already started (real start date is set)
- when tasks has somle "fix" mode : regular between dates or manual planning

But it seems there is an issue is some case on V8.5.5
We are investigating.


 
Posté : 18 Sep PM 17:099
Share:
Retour en haut