Hi,

I had some problems when I changed the dates to one activity in one of our projects (start and duration of validated dates).
After saving the changes ("automatic run plan" and "save dates" were che
cked), the start and finish dates were copied to planned dates, but no only to that activity, but every activity in the entire project.
I've been searching in the documentation and this forum for a "rollback" or something, but I couldn't find anything. Is there any way that I can recover my oldest dates? and why did this happened?

The project had requested dates only, with regular dependencies between activities, so I don't understand why this happened.
We are using Projeqtor 5.5.0 with MariaDB

Thanks,
Ignacio


 
Posté : 29/09/2016 10:45 pm
(@babynus)
Posts: 14952
Membre Admin
 

the start and finish dates were copied to planned dates, but no only to that activity, but every activity in the entire project.

In fact it is the reverse : planned dates are copied to validated dates.
And yes, the feature does exactly this for all activities of project

There is no "rollback" feature.
All you can do is rollback you database.

Another way is to export the activities into csv (from activities list), fix data in the csv (in Excel) and reimport the file.


 