Hello,
How can we give progress in for activities or tickets. We only have possibility for project. Is it possible to add this function if it is not available now (it is possible i dont see how updated status, but i see result but not list drop donw for select progress).
Thank you in advance for your answer.
Posté : 01/04/2017 10:42 am
Progress on activity is work driven : progress = real work / (real work + left work)
Posté : 02/04/2017 11:34 pm