Hello.
Is there a possibility to add a comment for each "real work" period?
I am used to teamwork's worklog that gives the possiblity to add a comment for each work period and indicate start and end times (for automatic calculation of time passed, for example)
This is very important for offline analysis of the progress of tasks and difficulties people had.
Is there a way to mimic this?
Hi,
Automatic calculation of time passed is only valid for tickets (short work).
Comment for real work period is available : there is a comment field in the real work allocation screen.
Hello.
Yes, I saw that there was a comment field.
However, it seems to be valid for the whole list of periods. I did not find how to set comment for each period, neither did i find how to set when a real work period starts.
I've been playing with demo not to make my install dirty but could not succeed.
it seems to be valid for the whole list of periods
It is valid for the selected week. Each week can have a specific comment
I did not find how to set comment for each period
Comment cannot be defined for each day.
neither did i find how to set when a real work period starts.
Real work start date is logged in the "real start date" of the activity.
Ok, thank you for your very precise answers.
I'll be filing a RFE so that this part of the software has a chance to be upgraded.
Best,