[#1420]

Hi,
I would like to be able to follow trends based on the values of:
- milestones dates
- riks values
- deliverables dates commited.

Is there a way to do that except by exporting monthly the values and recording them in a excel outside projector?

This is linked to the concept of baseline. Are you thinking about integrating it to Projector?
thanks.


 
Posted : 21 Oct 2013 14H37
(@babynus)
Posts: 14952
Member Admin
 

The baseline for milestone (and deliverables) dates are validated dates.
The baseline for risks is initial due date.


 
Posted : 21 Oct 2013 16H31