Hi,
I would like to know if there is any way to keep an history of the reassessed work ?
The aim is to follow, week after week, or month after month, how the reassessed work is growing or decreasing.
Regards,
Rémy
Did you look at baselines ?
I succeded in getting the data with the API, using the ProjectHistory table.
It would be great to have such report in a future version: evolution of RealWork + LeftWork during the time
I think it is what report "KPI Workload for project" does
I mean this kind of KPI

instead of this one "KPI Workload for project"

Understood.
Request recorded as Ticket #6412