Hello,
With this report I can see available working time when resources are in holidays
it's normal ?
Thanks
Anthony
All depneds on how you manage holidays...
If you use calendar for each resource : it's the wrong way, and it's normal the resources are considered vailable, as of Standerd calendar.
If you book holidays in an administrative project : it's the good way, and resource should then not be available.
Hello,
ok thanks
And yes I use calendar for resources who works 4 days/week (Cf. http://www.projeqtor.org/index.php/forum/3-propose-evolutions/5537-work-hours-for-each-resource-like-for-calendar)
but "RTT" days can't manage like this (because they are displayed available)
So, I need to create 1 holiday day/week ....
For example : with monday of non-working day in january ==> 8.75 hours availables...
My advise to book "RTT" is to define an Administrative project with RTT activity, and book real time for RTT.
Ok, thanks
But I don't understand utility of multiple calendar if you can't define non-working days on it
Anthony
You have multiple calendars, but not "individual" calendars.
Multiple calendars is done to be able to define different time frames.
For instance :
- a 80% timeframe, with all wednesdays off
- a tuesday to saturday timeframe (with monday off, saturday on)
- ...
Ok, but if I use like your exemple "a 80% timeframe, with all wednesdays off" in reports "availability of resources", wesnesday appear like avalaible time, no ?
YES, you're right !!!
:blush:
I'll have a look at this report ... 😉
Ticket #1278 recorded
😉
merci !