Thanks for your answer And what do you think about first part ? "If I check the box 'show closed items' in the 'project selector parameters' and a...
hello, Some more informations : If I check the box 'show closed items' in the 'project selector parameters' and after check the same box on the...
Ok, sorry...
Ok, but if I use like your exemple "a 80% timeframe, with all wednesdays off" in reports "availability of resources", wesnesday appear like avalaible ...
Ok, thanks But I don't understand utility of multiple calendar if you can't define non-working days on it Anthony
Hello, ok thanks And yes I use calendar for resources who works 4 days/week (Cf. but "RTT" days can't manage like this (because they are displ...
thanks for your help, your solution works perfectly !
" When you display work for all project in days, how is done conversion from hours to days for all resources ?" "For instance, define work period o...
Yes, "Open Workbench" can do this In fact, like Projeqtor, you can create calendar, but you can, in each calendar, chose numbers of working hours
For exemple I've in my team some people who works 5 days/week and 7 hours/day but I've other people who works 4 days/week and 8.75 hours/day I can...