Just to be sure, on the report "work synthesis per activity", what is the mean (or how is it calculate) for the following columns:
- Progress: It is real work / (planned work + left work)?
- Expected: It is real work / assigned work? => so if it is > 100%, a reassessed work was done?
Thanks
Posté : 2 Déc PM 12:1212
Progress: It is real work / (real work + left work) => little fix
Expected: It is real work / assigned work => Yes
> 100%, a reassessed work was done => Yes