I have several projects with activities, resources, affectations, rates but the resource planning stays empty.
Do I have to change any configuration ?
When i display the resource view, there is a planning related to affectations of this resource so there are datas.
Why my planning is empty ?
Thank you for your help because I'm blocked.
Bye !
Hello,
It's ok. In my affectations, there was a rate of 100% but the number of days was 0.
It's mandatory to give this number of day even if the rate is 100%.
My resource planning is now update.
Bye
Hi,
You're right : ProjeQtOt is effort driven. It means tasks are not planned if there is no work planned.
Only exception are tasks with planning mode "Fix duration".