Hi,

I have several projects with activities, resources, affectations, rates but the resource planning stays empty.
Do I have to change any configuration ?
When i display the resource view, there is a planning related to affectations of this resource so there are datas.
Why my planning is empty ?

Thank you for your help because I'm blocked.

Bye !


 
Posté : 16 Avr PM 20:044
(@nathalie-serieys)
Posts: 5
Active Member
Début du sujet
 

Hello,

It's ok. In my affectations, there was a rate of 100% but the number of days was 0.
It's mandatory to give this number of day even if the rate is 100%.

My resource planning is now update.

Bye


 
Posté : 17 Avr AM 11:044
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

You're right : ProjeQtOt is effort driven. It means tasks are not planned if there is no work planned.
Only exception are tasks with planning mode "Fix duration".


 
Posté : 17 Avr PM 12:044